Entitlements & Timeline
Austin timelines should be underwritten by risk profile. Clean by-right projects can still take significant time, while complex sites with rezoning, infrastructure, environmental, or neighborhood issues can run 3-5 years acquisition-to-CO.
Realistic Timelines
Core Risks
Key Tools
Contract + Go/No-Go Diligence
Title, survey, floodplain, Phase I ESA, trees, utilities, civil constraints, and entitlement risk memo.
Pre-Application + Feasibility
Concept plan, civil pre-screen, utility coordination, transportation scoping, and stakeholder outreach.
Entitlement / Public Process
Rezoning, CUP, density bonus, PUD, compatibility relief, or neighborhood-plan issues. Contested cases can run 18-36+ months.
Site Plan + Technical Review
DSD review, drainage, water quality, trees, TIA, fire access, utilities, and comment cycles. Complex sites can stretch 24-36+ months.
Construction + CO
Construction, utility tie-ins, ROW work, inspections, punch list, and certificate of occupancy.